Capital Projects and Park Planning...
2005 Land Preservation, Recreation and Parks Plan
Blandair Regional Park
North Laurel Community Center and Park
Robinson Nature Center
Land Management
Natural Resources...
Directions to Parks and Program Sites...
Employment Opportunities
Facilities and Pavilions
Forms and Publications
 

North Laurel Community Center and Park
Capital Projects C0304 and N3940

Project Description
Master Plan
Building Site Development Plan
Building Schematic Drawing
Project Budget
Tentative Project Schedule - Community Center
Tentative Project Schedule - Park Facilities
Project Schedule - Aquatic Center
Public Participation
Past and Future Public Meetings
Advisory Committee Meetings

Introduction

Howard County Recreation and Parks and the Department of Public Works have secured Construction Dynamics Group, Inc. (CDG) to design and construct the North Laurel Community Center. This firm will also develop a master plan for outdoor recreation facilities in conjunction with the Community Center. Click here for more information about CDG, Inc. and here for their approach to this project.

The Community Center and Park will be located south of Laurel Woods Elementary School on a 51-acre parcel of land owned by the County.
Site Location Map

In June of 2005 the 26-member North Laurel Community Center Planning Committee was assembled to assist with the design of the North Laurel Community Center and Park. This Committee is comprised of local residents with a sincere interest in making this facility a premier destination for the residents of North Laurel Park and surrounding neighborhoods. Not only do the Committee Members represent the interests of the surrounding communities, they also have knowledge of youth and adult recreation programs, facility design, environmental issues, public safety, and senior programming. Listed below are the members of the committee:

Gary J. Arthur, Director - Chair
Department of Recreation and Parks

Dave Loudermilk – County Project Manager
Department of Public Works

Members of the Community
Mariam Agrama, Lori Fuchs, Thomas Lawler, Barbara J. Lovett, Kenneth C. Miner, Patricia Moore, William R. Park, Jr., Pamela M. Peseux, Mary Talbot Rekus, Russell K. Snyder, David S. Steele, Donna Thewes

County and State Government Liaisons
Guy Guzzone, State Delegate
Jen Terrasa (or her designee), Council Representative

Department of Recreation & Parks Support Staff
Doris Bedsaul, Raul Delerme, Paul Walsky

Department of Planning & Zoning Support Staff
Dace Blaumanis

Department of Citizen Services Support Staff
Rachelle Garten, Starr Sowers

Department of Health
James Dunkerson

Department of Libraries Support Staff
Brian Auger, Valerie Gross

Police Department Representative
Officer Rocco Sovero

Recreation & Parks Advisory Board Representative
David Grabowski

Project Description

The proposed North Laurel Community Center is currently estimated to be a 60,000 square foot facility, similar to the new Glenwood Community Center located at Maryland Route 97 and Carrs Mill Road. The Glenwood facility opened for operation in October 2006. The Glenwood Center provides a model for the North Laurel Planning Committee to draw upon as they finalize a design program for the North Laurel facility. The North Laurel facility will be designed to meet the needs of North Laurel residents, thus we welcome public participation in the design process.

The Planning Committee, working closely with the County and CDG, Inc., has developed a preliminary design program. Click here to access the Building Program Summary. We encourage you to review the Summary and provide comments to our Department. Send comments.

New!
Presentation presented by the Consultant to The Planning Committee on March 26, 2008

In addition to the Community Center, the Planning Committee has recommended a variety of passive and active recreation facilities. Below is a list of facilities which the Planning Committee has recommended:

  • swimming pool or indoor aquatic center
  • athletic fields
  • skate park
  • basketball courts
  • tennis courts
  • volleyball court
  • playground
  • picnic shelters
  • pathways
  • roads, parking and storm water facilities

On November 16, 2006, a public meeting was held to gather input on three conceptual plans. With input from that meeting plus other public comments received, the Committee approved a final Master Plan on June 27, 2007. See below to view the approved Master Plan.

Master Plan

North Laurel Community Center and Park
Final Master Plan

Building Site Development Plan

North Laurel Community Center
Schematic Drawing (NEW!)

Building Schematic Drawing

North Laurel Community Center
Schematic Drawing (NEW!)

Project Budget

(Revised June 2008)

There are currently two existing capital projects to house the design and construction funds for the Community Center, and the Park facilities as follows:

Capital Project C0304 – North Laurel Community Center

Approved FY08 and Prior Design & Partial Construction Funding$ 5,290,000
Approved FY09 Construction Funding$14,260,000
Total for the Community Center$19,550,000

Capital Project N3940 – North Laurel Park

Approved Design Funds – FY08 and Prior$  191,000
Approved Construction Funds – FY07 and Prior$   60,000
Proposed Park Construction Funds FY09$  4,400,000
Proposed Park Construction Funds FY10$  1,000,000
Total for the Park $ 5,651,000

Tentative Project Schedule - Community Center

(Revised June 2008)

June 2007Finalize Master Plan
October 2008Public Progress Meeting – Community Center Rendering & Layout
December 2008Finalize Site Development Plan
February 2009Finalize Design of Community Center
April 2009Start Construction
October 2010Complete Construction

All dates are tentative and subject to change. As changes occur, the public will be informed on this web site.

Tentative Project Schedule - Park Facilities

(Revised June 2008)

November 16, 2006Public meeting at Murray Hill Middle School to discuss several conceptual site plans
June 2007Finalize Park Master Plan
January 2009Finalize Site Development Plan
April 2009Final Design of Park
June 2009Start Park Construction
February 2011Complete Park Construction

All dates are tentative and subject to change. As changes occur, the public will be informed on this web site.

Project Schedule - Aquatic Center

On hold pending the outcome of the Aquatics Feasibility Study commissioned by the Department of Recreation and Parks.

Public Participation

The Planning Committee, the County and the design consultant (CDG, Inc.) encourage the public to monitor this web site for project updates, attend public meetings and provide comments through this web site.

If you wish to comment on the information provided within this website, please contact Raul Delerme.

The County will also accept written comments directed to:

Gary J. Arthur, Director
Howard County Department of Recreation and Parks
7120 Oakland Mills Road
Columbia, MD 21046

You are also welcome to contact the Department’s Capital Project and Park Planning Division at 410-313-4685 for more information or to provide comments. Please follow this website for future updates including the dates for upcoming meetings.

We encourage you to be a part of this special project.

Past and Future Public Meetings

  • November 16, 2006 - Presented three conceptual plans for the park
  • December 13, 2006 – Citizen’s Budget Meeting. County Executive gathered public input for the FY2008 Capital Budget.
  • December 20, 2006 - Recreation and Parks Advisory Board conducted public hearing on the 2008 Capital Budget for Recreation and Parks.
  • February 15, 2007 - Planning Board conducted public hearing on FY2008 Capital Budget
  • April 19, 2007 – County Council conducted public hearing on the FY 2008 Capital Budget.
  • November 2007 (to be announced) – Public information meeting to present renderings of the Community Center and Park.
  • December 19, 2007 – Recreation and Parks Advisory Board will conduct a public hearing on the fiscal year 2009 Capital Budget at the Department’s Headquarters, 7120 Oakland Mills Road, Columbia, MD.
  • February 13, 2008 - Planning Board conducted public hearing on FY2009 Capital Budget

    Advisory Committee Meetings

    The Advisory Committee has concluded its meetings on the Master Plan for the Park and the Community Center. As the design develops, future meetings will be announced. These meetings will have a set agenda. The public is welcome to attend and observe as these meetings are posted. You are also welcome to submit written comments or questions to the committee. Please note that written comments and questions received during an Advisory Committee Meeting will not be discussed until the next committee meeting.

    Please monitor this web site for project updates.