About

After experiencing two historic floods in less than two years, Ellicott City was in desperate need of plan for flood mitigation that enhances public safety, retains the city's historic charm, and provides a sense of security to businesses, residents, and property owners. 

The Ellicott City Safe and Sound Plan encompasses those values as a guiding principle through its comprehensive and innovative approach to flood mitigation. The Plan outlines seven major infrastructure projects designed to reduce flooding in Historic Ellicott City. These projects include two water conveyance projects and five water detention projects throughout the watershed. When complete, these projects will work together to reduce the quantity and velocity of water on Main Street during major storm events.

Map of the Safe and Sound Flood Mitigation projects in Ellicott City.

Completed Projects

Projects In Construction

Projects in Design

Flood Mitigation Strategy

Frequently Asked Questions

Flood Mitigation Plan

How will the county pay for these projects?

We have been and continue to actively pursue state and federal grants, and are also using county funds to pay for the projects. Since taking office, County Executive Ball has worked with partners at the state and federal level to secure more than $300 million in funding for flood mitigation and related projects in Ellicott City. This includes a $75 million WIFIA loan through the Environmental Protection Agency and more than $75 million in state and federal grant funds.

 

When will construction be completed?

As of August 2025, two Safe and Sound projects have had construction completed: the H-7 and Quaker Mill Retention Ponds. The H-4 Pond is currently under construction and expected to be complete in Fall 2025. The Extended North Tunnel is under construction and expected to be complete in Fall 2027. Other projects will be completed as quickly as possible pending the completion of required design and permitting activities and pending funding availability.

 

What impact will these projects have on businesses and residents in Ellicott City and on the West End?

The largest impact will be around the construction of the Maryland Avenue Culvert, which could lead to road closures on Maryland Avenue. The exact impact is still being evaluated. Other projects should cause minimal or no impacts to businesses or residents in Ellicott City. For businesses and residents on the West End, temporary lane closures for the construction of the new culverts are anticipated.

 

When will acquisitions be completed?

All of the buildings on lower Main Street that the county intended to acquire have been purchased.

 

The county included the 100-year storm and the July 2016 in the analysis. Why didn't you show how the improvements would perform in the May 2018 storm?

Based on modelling data, the July 2016 storm produced the worst flooding so this storm was used to benchmark the flood mitigation options.

Capital Projects

What does it mean when a bid is advertised?

When a bid is advertised, a date is selected for interested and qualified contractors to submit a proposal for the work. This task is managed by the Office of Procurement and Contract Administration, which collects applicable technical documents, and posts the opportunity in the public domain.

 

What's the difference between preliminary design and final design?

Preliminary design generally includes activities to develop and evaluate concepts for the proposed work, and select a concept. This typically includes development of a conceptual cost estimate, as well as design and construction schedules which inform future budget requests. Final Design builds upon the preliminary design, and includes all technical documentation required to construct the project. This includes all required permitting.

 

Why do capital projects take so long?

Planning work for a significant Capital Project may start several years before an improvement is realized and involves several steps. There is typically also significant coordination required with external entities that can add to the overall timeline.

 

Why are you not showing expected completion dates for the projects?

Estimated completion dates are most accurate once the permitting and bid processes are complete. As more accurate information is available, the tracker will be updated.

County-Owned Building Restoration

Are there plans to rebuild Caplan’s?

Since the County has acquired the former Caplan’s Building, significant measures have been implemented to stabilize the front portion of the building. This includes removing flood debris, installing permanent shoring and bracing, and planning for future improvements. The County is constructing dry floodproofing at the new rear (south) side of the building and is proceeding with reconstruction of a resilient façade fronting Main Street. The Caplan's Building renovation is expected to be complete in Fall 2025. When complete, the Caplan's Building will be re-opened as a retail incubator space on Main Street, supporting small businesses and emerging entrepreneurs.

 

Why did Caplan’s get so damaged?

Caplan’s is situated at the bottom of the hill where Main Street turns, which makes Caplan’s both a focal point of the streetscape and more vulnerable to damage from flooding. Caplan’s is the first building along Lower Main Street that is built over the stream channel; and it has taken the brunt of the damage along the rear of the building from strong flood waters and storm debris.

 

What are the plans for the county-owned buildings on Lower Main Street?

The buildings purchased by the county will remain a public asset until all flood mitigation projects are complete. The portions of the building structures over the stream channel have been deconstructed and removed in order to remove constrictions on the stream channel.

The county completed a federal section 106 review in order to perform that work and is developing plans for renovation and reuse of those buildings. In the meantime, all of the building interiors have been cleared of storm debris and water-damaged finishes. Many storefronts along Main Street have been rebuilt with display windows in order to provide a weather resistant and attractive façade while final plans are developed and approved.

 

Can the existing buildings along Lower Main Street be restored to the pre-2018 flood conditions?

The buildings along Lower Main Street will need to change based on hydraulic studies. No first-floor structures can remain over the stream channels.

 

What work has been completed on Lower Main Street?

Extensive work has been ongoing on the county-owned buildings on Main Street:

  • All of the properties acquired by the county were initially assessed for structural integrity. Most buildings have also undergone some degree of clean out and/or repair activities.
  • New doors or windows were installed at 8081 Main Street (Tea on the Tiber), 8085 Main Street (Portalli’s), 8095 Main Street (Shoemaker Country) and 8111-8113 Main Street. Façade repairs and shadowboxes were also completed at 8085 Main Street, 8095 Main Street, and 8111-8113 Main Street.
  • Several buildings, including the former Caplan’s Department Store at 8125 Main Street had basements filled in to further ensure structural integrity. Mold remediation work was also completed as needed.

Stay Connected!

Sign up for the County Executive's weekly newsletter and stay up to date on everything Howard County.
 

Zip Code